Ti-5553 Engine Mount Pylon Drag Fitting

Product family: Engine-to-Wing Pylons.

Flow: Beta titanium forge → UT Volumetric Immersion → Heavy Hog-Out 5-Axis Ti → Finish Spherical Bore Grind → Penetrant FPI Darkroom → Laser Metrology Traveler → Nacelle & Pylon Sub-Assy

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: Ti-5553 Engine Mount Pylon Drag FittingSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Beta titanium forge → UT Volumetric Immersion (1,473 s) → Heavy Hog-Out 5-Axis Ti (1,915 s) → Finish Spherical Bore Grind (2,651 s) → Penetrant FPI Darkroom (2,013 s) → Laser Metrology Traveler (1,718 s) → Nacelle & Pylon Sub-Assy.SUPPLIERBeta titaniumforgeI2.18 d1UT VolumetricImmersionC/T 1,473 sI2.41 d2Heavy Hog-Out5-Axis TiC/T 1,915 sI2.82 d3Finish SphericalBore GrindC/T 2,651 sI2.18 d4Penetrant FPIDarkroomC/T 2,013 sI1.18 d5Laser MetrologyTravelerC/T 1,718 sI1.82 dCUSTOMERNacelle & PylonSub-Assy22 / parts

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. UT Volumetric Immersion1,473 s25 min96%99.4%4448 (2.18 d)34
2. Heavy Hog-Out 5-Axis Ti1,915 s35 min92%98.5%3353 (2.41 d)25
3. Finish Spherical Bore Grind2,651 s85 min83%95.0%2262 (2.82 d)15
4. Penetrant FPI Darkroom2,013 s30 min93%98.2%3348 (2.18 d)24
5. Laser Metrology Traveler1,718 s15 min95%97.6%1126 (1.18 d)28

Key figures

Takt time
2,455 s
Lead time
12.8 d
Value-added time
9,770 s
Process cycle efficiency (PCE)
1.4%
Rolled throughput yield (RTY)
89.1%
Customer demand per day
22 parts
Line capacity per day
15 parts
Bottleneck
Finish Spherical Bore Grind

Reading the bottleneck

The bottleneck is "Finish Spherical Bore Grind": it can process 15 parts per day against a demand of 22 parts, so it falls short of demand by 33.9%. Once downtime and scrap are counted, its cycle time grows from 2,651 s to 3,362 s, against a takt of 2,455 s. The largest loss at this step is equipment downtime (uptime 83%), about 543 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.