Nickel-Alloy 718 Satellite Thruster Chamber
Product family: Bipropellant Reaction Thrusters.
Flow: Superalloy bar producer → Swiss Turn Injector Dome → Electron-Beam Weld Skirt → Vacuum Anneal & Mill → Helium Mass-Spec Leak → CT-Scan Throat Passage → Spacecraft Propulsion Bay
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. Swiss Turn Injector Dome | 675 s | 25 min | 96% | 99.4% | 48 | 53 (2.21 d) | 37 |
| 2. Electron-Beam Weld Skirt | 878 s | 35 min | 92% | 98.5% | 36 | 58 (2.42 d) | 26 |
| 3. Vacuum Anneal & Mill | 1,215 s | 85 min | 83% | 95.0% | 24 | 67 (2.79 d) | 14 |
| 4. Helium Mass-Spec Leak | 923 s | 30 min | 93% | 98.2% | 36 | 53 (2.21 d) | 26 |
| 5. CT-Scan Throat Passage | 788 s | 15 min | 95% | 97.6% | 12 | 29 (1.21 d) | 30 |
Key figures
- Takt time
- 1,125 s
- Lead time
- 12.8 d
- Value-added time
- 4,479 s
- Process cycle efficiency (PCE)
- 1.3%
- Rolled throughput yield (RTY)
- 89.1%
- Customer demand per day
- 24 parts
- Line capacity per day
- 14 parts
- Bottleneck
- Vacuum Anneal & Mill
Reading the bottleneck
The bottleneck is "Vacuum Anneal & Mill": it can process 14 parts per day against a demand of 24 parts, so it falls short of demand by 40.8%. Once downtime and scrap are counted, its cycle time grows from 1,215 s to 1,541 s, against a takt of 1,125 s. The largest loss at this step is equipment downtime (uptime 83%), about 249 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of 5-Axis Aerospace Machining & NDT: 5-Axis Aerospace Machining & NDT
- Aerospace 5-Axis CNC & NDT Inspection
- Titanium Compressor Blisk 5-Axis Flank Mill
- Ultra-High-Strength 300M Landing Gear Piston
- 7075-T6 Aluminum Monolithic Wing Rib Line
- 30-Meter Long-Bed Wing Spar Milling
- Accessory Drive Gearbox Magnesium Casting
- Fly-by-Wire Titanium Hydraulic Manifold
- 15-5PH Stainless Flap Track Carriage
- Main Rotor Helicopter Swashplate Assembly
- Ti-5553 Engine Mount Pylon Drag Fitting
- 7150 Aluminum Extruded Cabin Seat Track