7150 Aluminum Extruded Cabin Seat Track

Product family: Widebody Floor Rail Tracks.

Flow: Aluminum extrusion house → Saw Length & End Mill → High-Speed Pitch Slot Punch → 5-Axis Lug & Weight Pocket → Sulfuric Clear Anodize → Go/No-Go Pin Pitch Gauge → Fuselage Floor Grid Line

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: 7150 Aluminum Extruded Cabin Seat TrackSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Aluminum extrusion house → Saw Length & End Mill (203 s) → High-Speed Pitch Slot Punch (263 s) → 5-Axis Lug & Weight Pocket (365 s) → Sulfuric Clear Anodize (277 s) → Go/No-Go Pin Pitch Gauge (236 s) → Fuselage Floor Grid Line.SUPPLIERAluminumextrusion houseI2.20 d1Saw Length & EndMillC/T 203 sI2.40 d2High-Speed PitchSlot PunchC/T 263 sI2.80 d35-Axis Lug &Weight PocketC/T 365 sI2.20 d4Sulfuric ClearAnodizeC/T 277 sI1.20 d5Go/No-Go PinPitch GaugeC/T 236 sI1.80 dCUSTOMERFuselage FloorGrid Line160 / parts

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Saw Length & End Mill203 s25 min96%99.4%320352 (2.20 d)250
2. High-Speed Pitch Slot Punch263 s35 min92%98.5%240384 (2.40 d)181
3. 5-Axis Lug & Weight Pocket365 s85 min83%95.0%160448 (2.80 d)106
4. Sulfuric Clear Anodize277 s30 min93%98.2%240352 (2.20 d)174
5. Go/No-Go Pin Pitch Gauge236 s15 min95%97.6%80192 (1.20 d)205

Key figures

Takt time
338 s
Lead time
12.6 d
Value-added time
1,344 s
Process cycle efficiency (PCE)
0.20%
Rolled throughput yield (RTY)
89.1%
Customer demand per day
160 parts
Line capacity per day
106 parts
Bottleneck
5-Axis Lug & Weight Pocket

Reading the bottleneck

The bottleneck is "5-Axis Lug & Weight Pocket": it can process 106 parts per day against a demand of 160 parts, so it falls short of demand by 34.0%. Once downtime and scrap are counted, its cycle time grows from 365 s to 463 s, against a takt of 338 s. The largest loss at this step is equipment downtime (uptime 83%), about 74.8 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.