Aerospace 5-Axis CNC & NDT Inspection

Product family: Ti-6Al-4V Structural Brackets.

Flow: Titanium alloy forge → Alloy Billet Cutting → Rough Mill & Stress Relief → 5-Axis CNC Milling → Thermal & Shot Peen → NDT & CMM Metrology → Tier-1 Aerostructures

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: Aerospace 5-Axis CNC & NDT InspectionSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Titanium alloy forge → Alloy Billet Cutting (810 s) → Rough Mill & Stress Relief (1,053 s) → 5-Axis CNC Milling (1,458 s) → Thermal & Shot Peen (1,107 s) → NDT & CMM Metrology (945 s) → Tier-1 Aerostructures.SUPPLIERTitanium alloyforgeI2.20 d1Alloy BilletCuttingC/T 810 sI2.40 d2Rough Mill &Stress ReliefC/T 1,053 sI2.80 d35-Axis CNCMillingC/T 1,458 sI2.20 d4Thermal & ShotPeenC/T 1,107 sI1.20 d5NDT & CMMMetrologyC/T 945 sI1.80 dCUSTOMERTier-1Aerostructures40 / brackets

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Alloy Billet Cutting810 s25 min96%99.4%8088 (2.20 d)63
2. Rough Mill & Stress Relief1,053 s35 min92%98.5%6096 (2.40 d)45
3. 5-Axis CNC Milling1,458 s85 min83%95.0%40112 (2.80 d)26
4. Thermal & Shot Peen1,107 s30 min93%98.2%6088 (2.20 d)44
5. NDT & CMM Metrology945 s15 min95%97.6%2048 (1.20 d)51

Key figures

Takt time
1,350 s
Lead time
12.7 d
Value-added time
5,373 s
Process cycle efficiency (PCE)
0.78%
Rolled throughput yield (RTY)
89.1%
Customer demand per day
40 brackets
Line capacity per day
26 brackets
Bottleneck
5-Axis CNC Milling

Reading the bottleneck

The bottleneck is "5-Axis CNC Milling": it can process 26 brackets per day against a demand of 40 brackets, so it falls short of demand by 33.9%. Once downtime and scrap are counted, its cycle time grows from 1,458 s to 1,849 s, against a takt of 1,350 s. The largest loss at this step is equipment downtime (uptime 83%), about 299 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.