Titanium Compressor Blisk 5-Axis Flank Mill

Product family: Monolithic Engine Blisks.

Flow: Specialty titanium-alloy producer → Ultrasonic Billet Turn → Airfoil Rough Slot EDM/Mill → 5-Axis Flank Airfoil Finish → Micro-Polish & Shot Peen → Blue-Light 3D Blade Scan → Turbofan Fan Module Line

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: Titanium Compressor Blisk 5-Axis Flank MillSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Specialty titanium-alloy producer → Ultrasonic Billet Turn (4,050 s) → Airfoil Rough Slot EDM/Mill (5,265 s) → 5-Axis Flank Airfoil Finish (7,290 s) → Micro-Polish & Shot Peen (5,535 s) → Blue-Light 3D Blade Scan (4,725 s) → Turbofan Fan Module Line.SUPPLIERSpecialtytitanium-alloyproducerI2.17 d1Ultrasonic BilletTurnC/T 4,050 sI2.42 d2Airfoil RoughSlot EDM/MillC/T 5,265 sI2.83 d35-Axis FlankAirfoil FinishC/T 7,290 sI2.17 d4Micro-Polish &Shot PeenC/T 5,535 sI1.17 d5Blue-Light 3DBlade ScanC/T 4,725 sI1.83 dCUSTOMERTurbofan FanModule Line12 / parts

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Ultrasonic Billet Turn4,050 s25 min96%99.4%2426 (2.17 d)19
2. Airfoil Rough Slot EDM/Mill5,265 s35 min92%98.5%1829 (2.42 d)14
3. 5-Axis Flank Airfoil Finish7,290 s85 min83%95.0%1234 (2.83 d)8
4. Micro-Polish & Shot Peen5,535 s30 min93%98.2%1826 (2.17 d)13
5. Blue-Light 3D Blade Scan4,725 s15 min95%97.6%614 (1.17 d)16

Key figures

Takt time
6,750 s
Lead time
12.9 d
Value-added time
26,865 s
Process cycle efficiency (PCE)
2.6%
Rolled throughput yield (RTY)
89.1%
Customer demand per day
12 parts
Line capacity per day
8 parts
Bottleneck
5-Axis Flank Airfoil Finish

Reading the bottleneck

The bottleneck is "5-Axis Flank Airfoil Finish": it can process 8 parts per day against a demand of 12 parts, so it falls short of demand by 31.6%. Once downtime and scrap are counted, its cycle time grows from 7,290 s to 9,245 s, against a takt of 6,750 s. The largest loss at this step is equipment downtime (uptime 83%), about 1,493 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.