Aircraft MRO & Heavy Overhaul VSM Scenarios
12 scenarios of Aircraft MRO & Heavy Overhaul, built on the same five steps. They differ by scale: demand, shifts, cycle times and buffers.
Shared steps
All 12 scenarios follow the same flow, from supplier to customer: Induction Strip & Borescope → Chemical Paint Strip & Clean → Non-Routine Structural Repair → Reassembly & Rigging Check → Form-1 CRS Release Sign-off. What changes from one scenario to the next is the volume and the pace, so the same step can be the constraint in one scenario and not in another.
Scenario comparison
Choose the scenario closest to your daily demand and shift pattern, then adjust the figures in the editor. All values are illustrative starting points.
| Scenario | Demand | Shifts | Takt | Lead time | PCE | Bottleneck |
|---|---|---|---|---|---|---|
| Narrowbody A320/737 Heavy C-Check Hangar | 4 cases per day | 2 | 17,100 s | 10.5 d | 9.5% | Non-Routine Structural Fix |
| High-Bypass Turbofan Full Performance Overhaul | 3 units per day | 2 | 22,800 s | 10.3 d | 12.8% | Blade Weld & Tip Grind NRC |
| Widebody Landing Gear 10-Year Overhaul Bay | 4 assemblies per day | 2 | 17,100 s | 10.5 d | 9.5% | 300M Bush Bore & Chrome Grind |
| Part-145 Avionics LRU Bench Repair & Mod | 28 units per day | 1 | 1,221 s | 9.50 d | 1.5% | Conformal Touch-Up & Bake |
| Commercial APU Turbine Hot-Section Overhaul | 10 units per day | 2 | 6,840 s | 9.80 d | 4.1% | Hot-Section Seal Re-Blade |
| Weather Radome Moisture & RF Transmission Fix | 12 units per day | 1 | 2,850 s | 9.83 d | 3.4% | Quartz Patch Vacuum Cure |
| Widebody Whole-Aircraft Strip & Livery Paint | 2 units per day | 3 | 51,300 s | 12.0 d | 16.6% | Epoxy Primer Electro-Coat |
| Business-Class Lie-Flat Seat Refurbishment | 32 units per day | 2 | 2,138 s | 9.56 d | 1.3% | FR Leather Dress-Cover Fit |
| Composite Thrust Reverser Acoustic Patch | 8 units per day | 2 | 8,550 s | 9.75 d | 5.1% | Hot-Bonder Vacuum Cure Patch |
| High-Temp Bleed Air & Starter Valve Rebuild | 44 units per day | 1 | 777 s | 9.50 d | 0.95% | Spring & Actuator Calibration |
| Carbon Disc Wheel & Brake MRO Turnaround | 85 units per day | 2 | 805 s | 9.45 d | 0.50% | Bead-Seat Seal & New Nitrogen |
| Turboprop 6-Blade Composite Propeller Overhaul | 10 assemblies per day | 1 | 3,420 s | 9.80 d | 4.1% | Blade Erosion Boot & Balance |