High-Bypass Turbofan Full Performance Overhaul
Product family: 5000-Cycle Core Overhauls.
Flow: Airlines & Engine Lessors → Complete Module Teardown → Chem Strip, FPI & X-Ray Inspect → Blade Weld & Tip Grind NRC → Fan/Core/LPT Module Build → Sea-Level Pass-Off Run Cell → Airline Fleet Pools
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. Complete Module Teardown | 15,960 s | 20 min | 95% | 97.5% | 2 | 4 (1.33 d) | 4 |
| 2. Chem Strip, FPI & X-Ray Inspect | 17,784 s | 25 min | 92% | 98.1% | 2 | 5 (1.67 d) | 3 |
| 3. Blade Weld & Tip Grind NRC | 25,080 s | 40 min | 82% | 91.5% | 3 | 10 (3.33 d) | 2 |
| 4. Fan/Core/LPT Module Build | 18,240 s | 20 min | 93% | 97.6% | 1 | 4 (1.33 d) | 3 |
| 5. Sea-Level Pass-Off Run Cell | 13,680 s | 10 min | 97% | 99.1% | 1 | 2 (0.67 d) | 5 |
Key figures
- Takt time
- 22,800 s
- Lead time
- 10.3 d
- Value-added time
- 90,744 s
- Process cycle efficiency (PCE)
- 12.8%
- Rolled throughput yield (RTY)
- 84.6%
- Customer demand per day
- 3 units
- Line capacity per day
- 2 units
- Bottleneck
- Blade Weld & Tip Grind NRC
Reading the bottleneck
The bottleneck is "Blade Weld & Tip Grind NRC": it can process 2 units per day against a demand of 3 units, so it falls short of demand by 34.2%. Once downtime and scrap are counted, its cycle time grows from 25,080 s to 33,427 s, against a takt of 22,800 s. The largest loss at this step is equipment downtime (uptime 82%), about 5,505 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of Aircraft MRO & Heavy Overhaul: Aircraft MRO & Heavy Overhaul
- Narrowbody A320/737 Heavy C-Check Hangar
- Widebody Landing Gear 10-Year Overhaul Bay
- Part-145 Avionics LRU Bench Repair & Mod
- Commercial APU Turbine Hot-Section Overhaul
- Weather Radome Moisture & RF Transmission Fix
- Widebody Whole-Aircraft Strip & Livery Paint
- Business-Class Lie-Flat Seat Refurbishment
- Composite Thrust Reverser Acoustic Patch
- High-Temp Bleed Air & Starter Valve Rebuild
- Carbon Disc Wheel & Brake MRO Turnaround
- Turboprop 6-Blade Composite Propeller Overhaul