Commercial APU Turbine Hot-Section Overhaul

Product family: Zero-Time Repaired APUs.

Flow: Operator Rotable Spares → Intake & Gearbox Split → Impeller FPI & Housing Blend → Hot-Section Seal Re-Blade → Rig Fuel Control & Starter → 4-Hour Load Bank Test Cell → Regional & Narrowbody Fleets

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: Commercial APU Turbine Hot-Section OverhaulSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Operator Rotable Spares → Intake & Gearbox Split (4,788 s) → Impeller FPI & Housing Blend (5,335 s) → Hot-Section Seal Re-Blade (7,524 s) → Rig Fuel Control & Starter (5,472 s) → 4-Hour Load Bank Test Cell (4,104 s) → Regional & Narrowbody Fleets.SUPPLIEROperatorRotable SparesI1.40 d1Intake & GearboxSplitC/T 4,788 sI1.80 d2Impeller FPI &Housing BlendC/T 5,335 sI3.20 d3Hot-Section SealRe-BladeC/T 7,524 sI1.40 d4Rig Fuel Control& StarterC/T 5,472 sI0.80 d54-Hour Load BankTest CellC/T 4,104 sI0.80 dCUSTOMERRegional &Narrowbody…10 / units

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Intake & Gearbox Split4,788 s20 min95%97.5%514 (1.40 d)13
2. Impeller FPI & Housing Blend5,335 s25 min92%98.1%818 (1.80 d)11
3. Hot-Section Seal Re-Blade7,524 s40 min82%91.5%1032 (3.20 d)7
4. Rig Fuel Control & Starter5,472 s20 min93%97.6%414 (1.40 d)11
5. 4-Hour Load Bank Test Cell4,104 s10 min97%99.1%28 (0.80 d)15

Key figures

Takt time
6,840 s
Lead time
9.80 d
Value-added time
27,223 s
Process cycle efficiency (PCE)
4.1%
Rolled throughput yield (RTY)
84.6%
Customer demand per day
10 units
Line capacity per day
7 units
Bottleneck
Hot-Section Seal Re-Blade

Reading the bottleneck

The bottleneck is "Hot-Section Seal Re-Blade": it can process 7 units per day against a demand of 10 units, so it falls short of demand by 34.2%. Once downtime and scrap are counted, its cycle time grows from 7,524 s to 10,028 s, against a takt of 6,840 s. The largest loss at this step is equipment downtime (uptime 82%), about 1,652 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.