Part-145 Avionics LRU Bench Repair & Mod

Product family: Recertified Flight LRUs.

Flow: Airline Line Stations → Bench Diagnostics & Log Read → BGA Rework & Mod Kit Apply → Conformal Touch-Up & Bake → ATE Automated Test Sweep → Dual EASA/FAA 8130 Tag → Global AOG Parts Desk

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: Part-145 Avionics LRU Bench Repair & ModSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Airline Line Stations → Bench Diagnostics & Log Read (855 s) → BGA Rework & Mod Kit Apply (953 s) → Conformal Touch-Up & Bake (1,344 s) → ATE Automated Test Sweep (977 s) → Dual EASA/FAA 8130 Tag (733 s) → Global AOG Parts Desk.SUPPLIERAirline LineStationsI1.39 d1Bench Diagnostics& Log ReadC/T 855 sI1.79 d2BGA Rework & ModKit ApplyC/T 953 sI3.21 d3ConformalTouch-Up & BakeC/T 1,344 sI1.39 d4ATE AutomatedTest SweepC/T 977 sI0.79 d5Dual EASA/FAA8130 TagC/T 733 sI0.79 dCUSTOMERGlobal AOGParts Desk28 / units

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Bench Diagnostics & Log Read855 s20 min95%97.5%1439 (1.39 d)34
2. BGA Rework & Mod Kit Apply953 s25 min92%98.1%2250 (1.79 d)31
3. Conformal Touch-Up & Bake1,344 s40 min82%91.5%2890 (3.21 d)18
4. ATE Automated Test Sweep977 s20 min93%97.6%1139 (1.39 d)29
5. Dual EASA/FAA 8130 Tag733 s10 min97%99.1%622 (0.79 d)41

Key figures

Takt time
1,221 s
Lead time
9.50 d
Value-added time
4,862 s
Process cycle efficiency (PCE)
1.5%
Rolled throughput yield (RTY)
84.6%
Customer demand per day
28 units
Line capacity per day
18 units
Bottleneck
Conformal Touch-Up & Bake

Reading the bottleneck

The bottleneck is "Conformal Touch-Up & Bake": it can process 18 units per day against a demand of 28 units, so it falls short of demand by 36.6%. Once downtime and scrap are counted, its cycle time grows from 1,344 s to 1,791 s, against a takt of 1,221 s. The largest loss at this step is equipment downtime (uptime 82%), about 295 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.