Business-Class Lie-Flat Seat Refurbishment

Product family: Cabin Interior LOPA Retrofit.

Flow: Airline Cabin Programs → Seat Teardown & Track Check → Harness & Recline Actuator Fix → FR Leather Dress-Cover Fit → IFE Screen Rewire & Trim → 9G Burn Cert & Load Tag → Airline Interior MRO

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: Business-Class Lie-Flat Seat RefurbishmentSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Airline Cabin Programs → Seat Teardown & Track Check (1,496 s) → Harness & Recline Actuator Fix (1,667 s) → FR Leather Dress-Cover Fit (2,351 s) → IFE Screen Rewire & Trim (1,710 s) → 9G Burn Cert & Load Tag (1,283 s) → Airline Interior MRO.SUPPLIERAirline CabinProgramsI1.41 d1Seat Teardown &Track CheckC/T 1,496 sI1.81 d2Harness & ReclineActuator FixC/T 1,667 sI3.19 d3FR LeatherDress-Cover FitC/T 2,351 sI1.41 d4IFE Screen Rewire& TrimC/T 1,710 sI0.81 d59G Burn Cert &Load TagC/T 1,283 sI0.81 dCUSTOMERAirlineInterior MRO32 / units

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Seat Teardown & Track Check1,496 s20 min95%97.5%1645 (1.41 d)41
2. Harness & Recline Actuator Fix1,667 s25 min92%98.1%2658 (1.81 d)36
3. FR Leather Dress-Cover Fit2,351 s40 min82%91.5%32102 (3.19 d)21
4. IFE Screen Rewire & Trim1,710 s20 min93%97.6%1345 (1.41 d)35
5. 9G Burn Cert & Load Tag1,283 s10 min97%99.1%626 (0.81 d)49

Key figures

Takt time
2,138 s
Lead time
9.56 d
Value-added time
8,507 s
Process cycle efficiency (PCE)
1.3%
Rolled throughput yield (RTY)
84.6%
Customer demand per day
32 units
Line capacity per day
21 units
Bottleneck
FR Leather Dress-Cover Fit

Reading the bottleneck

The bottleneck is "FR Leather Dress-Cover Fit": it can process 21 units per day against a demand of 32 units, so it falls short of demand by 34.2%. Once downtime and scrap are counted, its cycle time grows from 2,351 s to 3,133 s, against a takt of 2,138 s. The largest loss at this step is equipment downtime (uptime 82%), about 516 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.