High-Temp Bleed Air & Starter Valve Rebuild

Product family: Pneumatic ATA-36 Valves.

Flow: Rotables Brokers → Ultrasonic Carbon Decoke → Piston & Butterfly Seal Lap → Spring & Actuator Calibration → 750°F High-Temp Leak Bench → 8130-3 Airworthiness Release → Line Maintenance Pools

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: High-Temp Bleed Air & Starter Valve RebuildSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Rotables Brokers → Ultrasonic Carbon Decoke (544 s) → Piston & Butterfly Seal Lap (606 s) → Spring & Actuator Calibration (855 s) → 750°F High-Temp Leak Bench (622 s) → 8130-3 Airworthiness Release (466 s) → Line Maintenance Pools.SUPPLIERRotablesBrokersI1.41 d1Ultrasonic CarbonDecokeC/T 544 sI1.80 d2Piston &Butterfly Seal…C/T 606 sI3.20 d3Spring & ActuatorCalibrationC/T 855 sI1.41 d4750°F High-TempLeak BenchC/T 622 sI0.80 d58130-3Airworthiness…C/T 466 sI0.80 dCUSTOMERLineMaintenance…44 / units

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Ultrasonic Carbon Decoke544 s20 min95%97.5%2262 (1.41 d)54
2. Piston & Butterfly Seal Lap606 s25 min92%98.1%3579 (1.80 d)48
3. Spring & Actuator Calibration855 s40 min82%91.5%44141 (3.20 d)28
4. 750°F High-Temp Leak Bench622 s20 min93%97.6%1862 (1.41 d)46
5. 8130-3 Airworthiness Release466 s10 min97%99.1%935 (0.80 d)64

Key figures

Takt time
777 s
Lead time
9.50 d
Value-added time
3,093 s
Process cycle efficiency (PCE)
0.95%
Rolled throughput yield (RTY)
84.6%
Customer demand per day
44 units
Line capacity per day
28 units
Bottleneck
Spring & Actuator Calibration

Reading the bottleneck

The bottleneck is "Spring & Actuator Calibration": it can process 28 units per day against a demand of 44 units, so it falls short of demand by 36.6%. Once downtime and scrap are counted, its cycle time grows from 855 s to 1,140 s, against a takt of 777 s. The largest loss at this step is equipment downtime (uptime 82%), about 188 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.