Carbon Disc Wheel & Brake MRO Turnaround

Product family: Aircraft Wheel & Carbon Stacks.

Flow: Turnaround Line Stations → Deflate, Dismount & Clean → Eddy Current Rim Wheel Check → Bead-Seat Seal & New Nitrogen → Carbon Rotor Thickness Wear Check → Leak & Torque Roll-Out → Airline Hub Ramp

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: Carbon Disc Wheel & Brake MRO TurnaroundSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Turnaround Line Stations → Deflate, Dismount & Clean (563 s) → Eddy Current Rim Wheel Check (628 s) → Bead-Seat Seal & New Nitrogen (885 s) → Carbon Rotor Thickness Wear Check (644 s) → Leak & Torque Roll-Out (483 s) → Airline Hub Ramp.SUPPLIERTurnaround LineStationsI1.40 d1Deflate, Dismount& CleanC/T 563 sI1.80 d2Eddy Current RimWheel CheckC/T 628 sI3.20 d3Bead-Seat Seal &New NitrogenC/T 885 sI1.40 d4Carbon RotorThickness Wear…C/T 644 sI0.80 d5Leak & TorqueRoll-OutC/T 483 sI0.80 dCUSTOMERAirline HubRamp85 / units

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Deflate, Dismount & Clean563 s20 min95%97.5%43119 (1.40 d)109
2. Eddy Current Rim Wheel Check628 s25 min92%98.1%68153 (1.80 d)96
3. Bead-Seat Seal & New Nitrogen885 s40 min82%91.5%85272 (3.20 d)56
4. Carbon Rotor Thickness Wear Check644 s20 min93%97.6%34119 (1.40 d)92
5. Leak & Torque Roll-Out483 s10 min97%99.1%1768 (0.80 d)130

Key figures

Takt time
805 s
Lead time
9.45 d
Value-added time
3,203 s
Process cycle efficiency (PCE)
0.50%
Rolled throughput yield (RTY)
84.6%
Customer demand per day
85 units
Line capacity per day
56 units
Bottleneck
Bead-Seat Seal & New Nitrogen

Reading the bottleneck

The bottleneck is "Bead-Seat Seal & New Nitrogen": it can process 56 units per day against a demand of 85 units, so it falls short of demand by 34.2%. Once downtime and scrap are counted, its cycle time grows from 885 s to 1,180 s, against a takt of 805 s. The largest loss at this step is equipment downtime (uptime 82%), about 194 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.