OSAT Flip-Chip BGA & 2.5D Interposer Pack
Product family: High-Pin-Count AI Chipsets.
Flow: Build-Up Film Substrate Suppliers → Ultra-Thin Wafer Backgrind → Stealth Laser Wafer Dicing → Thermo-Comp Flip-Chip Bond → Capillary Underfill & Mold → Solder Ball Drop & FT ATE → AI Accelerator Chipmakers
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. Ultra-Thin Wafer Backgrind | 3.1 s | 20 min | 96% | 99.1% | 18,000 | 28,800 (1.60 d) | 24,490 |
| 2. Stealth Laser Wafer Dicing | 4.9 s | 35 min | 83% | 94.8% | 21,600 | 46,800 (2.60 d) | 12,726 |
| 3. Thermo-Comp Flip-Chip Bond | 3.8 s | 25 min | 90% | 97.4% | 14,400 | 34,200 (1.90 d) | 18,253 |
| 4. Capillary Underfill & Mold | 3.5 s | 20 min | 92% | 98.0% | 10,800 | 27,000 (1.50 d) | 20,350 |
| 5. Solder Ball Drop & FT ATE | 2.9 s | 15 min | 95% | 96.8% | 7,200 | 19,800 (1.10 d) | 24,972 |
Key figures
- Takt time
- 4.5 s
- Lead time
- 10.2 d
- Value-added time
- 18.2 s
- Process cycle efficiency (PCE)
- 0.002%
- Rolled throughput yield (RTY)
- 86.8%
- Customer demand per day
- 18,000 units
- Line capacity per day
- 12,726 units
- Bottleneck
- Stealth Laser Wafer Dicing
Reading the bottleneck
The bottleneck is "Stealth Laser Wafer Dicing": it can process 12,726 units per day against a demand of 18,000 units, so it falls short of demand by 29.3%. Once downtime and scrap are counted, its cycle time grows from 4.9 s to 6.2 s, against a takt of 4.5 s. The largest loss at this step is equipment downtime (uptime 83%), about 1.0 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of Semiconductors & Wafer Fab: Semiconductors & Wafer Fab
- 5nm/3nm FinFET 300mm Wafer Logic Fab Line
- 1200V Silicon Carbide (SiC) EV MOSFET Fab
- GaN-on-SiC 5G RF Power Amplifier Foundry
- 6-Axis Automotive IMU MEMS Sensor Wafer
- QFN / SOIC Copper-Wire Molded IC Assembly
- Tri-Temp Burn-In & Automated IC Final Test
- PVT Silicon Carbide Crystal Growth & Wire Saw
- EUV Phase-Shift Photomask Blank & Write
- Mini-SMD 1.6x1.2mm Quartz Crystal Resonator
- Sapphire-Wafer GaN Micro-LED Epi & Chip
- Dual-Sided Sintered SiC Half-Bridge Module