PVT Silicon Carbide Crystal Growth & Wire Saw

Product family: Low-Micropipe 200mm SiC Boules.

Flow: High-Purity Si & Graphite → 2200°C PVT Seed Crystal Grow → OD Grind & Flat Orientation → Diamond Multi-Wire Wafer Saw → Lapping & Laser Edge Bevel → KOH Defect & Bow Inspection → SiC Wafer Epi Fabs

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: PVT Silicon Carbide Crystal Growth & Wire SawSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. High-Purity Si & Graphite → 2200°C PVT Seed Crystal Grow (630 s) → OD Grind & Flat Orientation (972 s) → Diamond Multi-Wire Wafer Saw (756 s) → Lapping & Laser Edge Bevel (702 s) → KOH Defect & Bow Inspection (576 s) → SiC Wafer Epi Fabs.SUPPLIERHigh-Purity Si& GraphiteI1.60 d12200°C PVT SeedCrystal GrowC/T 630 sI2.60 d2OD Grind & FlatOrientationC/T 972 sI1.90 d3DiamondMulti-Wire Wafer…C/T 756 sI1.50 d4Lapping & LaserEdge BevelC/T 702 sI1.10 d5KOH Defect & BowInspectionC/T 576 sI1.50 dCUSTOMERSiC Wafer EpiFabs90 / batches

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. 2200°C PVT Seed Crystal Grow630 s20 min96%99.1%90144 (1.60 d)121
2. OD Grind & Flat Orientation972 s35 min83%94.8%108234 (2.60 d)64
3. Diamond Multi-Wire Wafer Saw756 s25 min90%97.4%72171 (1.90 d)92
4. Lapping & Laser Edge Bevel702 s20 min92%98.0%54135 (1.50 d)101
5. KOH Defect & Bow Inspection576 s15 min95%96.8%3699 (1.10 d)126

Key figures

Takt time
900 s
Lead time
10.2 d
Value-added time
3,636 s
Process cycle efficiency (PCE)
0.44%
Rolled throughput yield (RTY)
86.8%
Customer demand per day
90 batches
Line capacity per day
64 batches
Bottleneck
OD Grind & Flat Orientation

Reading the bottleneck

The bottleneck is "OD Grind & Flat Orientation": it can process 64 batches per day against a demand of 90 batches, so it falls short of demand by 28.7%. Once downtime and scrap are counted, its cycle time grows from 972 s to 1,235 s, against a takt of 900 s. The largest loss at this step is equipment downtime (uptime 83%), about 199 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.