Mini-SMD 1.6x1.2mm Quartz Crystal Resonator
Product family: TCXO Clock References.
Flow: Quartz Blank Suppliers → Hydrothermal Wafer Saw & Lap → Vacuum Gold Electrode Sputter → Ceramic Seam-Seal Cavity Fit → Laser Frequency Micro-Trim → Temp-Curve TCXO Grade Sort → 5G, Smartphones & GNSS
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. Hydrothermal Wafer Saw & Lap | 1.2 s | 20 min | 96% | 99.1% | 60,000 | 96,000 (1.60 d) | 63,265 |
| 2. Vacuum Gold Electrode Sputter | 1.5 s | 35 min | 83% | 94.8% | 72,000 | 156,000 (2.60 d) | 41,571 |
| 3. Ceramic Seam-Seal Cavity Fit | 1.2 s | 25 min | 90% | 97.4% | 48,000 | 114,000 (1.90 d) | 57,801 |
| 4. Laser Frequency Micro-Trim | 1.2 s | 20 min | 92% | 98.0% | 36,000 | 90,000 (1.50 d) | 59,355 |
| 5. Temp-Curve TCXO Grade Sort | 1.2 s | 15 min | 95% | 96.8% | 24,000 | 66,000 (1.10 d) | 60,349 |
Key figures
- Takt time
- 1.4 s
- Lead time
- 10.2 d
- Value-added time
- 6.3 s
- Process cycle efficiency (PCE)
- 0.001%
- Rolled throughput yield (RTY)
- 86.8%
- Customer demand per day
- 60,000 units
- Line capacity per day
- 41,571 units
- Bottleneck
- Vacuum Gold Electrode Sputter
Reading the bottleneck
The bottleneck is "Vacuum Gold Electrode Sputter": it can process 41,571 units per day against a demand of 60,000 units, so it falls short of demand by 30.7%. Once downtime and scrap are counted, its cycle time grows from 1.5 s to 1.9 s, against a takt of 1.4 s. The largest loss at this step is equipment downtime (uptime 83%), about 0.3 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of Semiconductors & Wafer Fab: Semiconductors & Wafer Fab
- 5nm/3nm FinFET 300mm Wafer Logic Fab Line
- 1200V Silicon Carbide (SiC) EV MOSFET Fab
- GaN-on-SiC 5G RF Power Amplifier Foundry
- 6-Axis Automotive IMU MEMS Sensor Wafer
- OSAT Flip-Chip BGA & 2.5D Interposer Pack
- QFN / SOIC Copper-Wire Molded IC Assembly
- Tri-Temp Burn-In & Automated IC Final Test
- PVT Silicon Carbide Crystal Growth & Wire Saw
- EUV Phase-Shift Photomask Blank & Write
- Sapphire-Wafer GaN Micro-LED Epi & Chip
- Dual-Sided Sintered SiC Half-Bridge Module