100% Hydrogen Direct-Reduced Iron (H2-DRI) EAF
Product family: Near-Zero Fossil Flat Steel.
Flow: DR-Grade Pellets & Green H2 → 100% H2 Shaft Furnace Reduc → Hot-Charged EAF Electric Melt → Argon Ladle Secondary Refine → Thin-Slab Continuous Caster → EPD Verified Low-CO2 Coil Tag → Automotive Low-CO2 Coils
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. 100% H2 Shaft Furnace Reduc | 85.0 s | 20 min | 94% | 98.2% | 650 | 910 (1.40 d) | 867 |
| 2. Hot-Charged EAF Electric Melt | 105 s | 30 min | 91% | 97.4% | 650 | 1,040 (1.60 d) | 669 |
| 3. Argon Ladle Secondary Refine | 133 s | 40 min | 84% | 95.8% | 650 | 1,300 (2.00 d) | 476 |
| 4. Thin-Slab Continuous Caster | 90.0 s | 10 min | 96% | 98.6% | 260 | 585 (0.90 d) | 836 |
| 5. EPD Verified Low-CO2 Coil Tag | 67.0 s | 8 min | 97% | 99.4% | 195 | 455 (0.70 d) | 1,143 |
Key figures
- Takt time
- 125 s
- Lead time
- 7.81 d
- Value-added time
- 480 s
- Process cycle efficiency (PCE)
- 0.076%
- Rolled throughput yield (RTY)
- 89.8%
- Customer demand per day
- 650 tonnes
- Line capacity per day
- 476 tonnes
- Bottleneck
- Argon Ladle Secondary Refine
Reading the bottleneck
The bottleneck is "Argon Ladle Secondary Refine": it can process 476 tonnes per day against a demand of 650 tonnes, so it falls short of demand by 26.8%. Once downtime and scrap are counted, its cycle time grows from 133 s to 165 s, against a takt of 125 s. The largest loss at this step is equipment downtime (uptime 84%), about 25.3 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of Decarbonization, Green Steel & Circular ESG: Decarbonization, Green Steel & Circular ESG
- Direct Air Capture (DAC) Solid-Sorbent CO2 Pod
- Continuous Biomass Pyrolysis Biochar Carbon Sink
- Cement Flue-Gas Post-Combustion Amine CCUS
- Closed-Loop Beverage Can-to-Can Al Remelt Line
- Used Cooking Oil (UCO) to Sustainable Aviation Fuel
- Black-Mass Lithium, Cobalt & Nickel Hydromet
- Captured CO2 + Green H2 e-Methanol Synthesis
- Automated Product Carbon Footprint (PCF) ISO-14067
- Industrial Waste-Heat Upgrade 150°C Steam Pump
- End-of-Life Solar PV Glass, Silver & Si Recovery
- EU CBAM & EUDR Deforestation Supply-Chain Gate