Industrial Waste-Heat Upgrade 150°C Steam Pump

Product family: Electrified Factory Process Heat.

Flow: Clean Coolant Loops 40°C → Source HX Titanium Welding → 2-Stage High-Temp Compressor → Flash Tank Steam Separator → SCADA COP >3.2 Commissioning → Gas Boiler Offset Meter Verify → Dairy & Paper Drying Lines

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: Industrial Waste-Heat Upgrade 150°C Steam PumpSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Clean Coolant Loops 40°C → Source HX Titanium Welding (3,060 s) → 2-Stage High-Temp Compressor (3,780 s) → Flash Tank Steam Separator (4,815 s) → SCADA COP >3.2 Commissioning (3,240 s) → Gas Boiler Offset Meter Verify (2,430 s) → Dairy & Paper Drying Lines.SUPPLIERClean CoolantLoops 40°CI1.33 d1Source HXTitanium WeldingC/T 3,060 sI1.67 d22-Stage High-TempCompressorC/T 3,780 sI2.00 d3Flash Tank SteamSeparatorC/T 4,815 sI0.83 d4SCADA COP >3.2CommissioningC/T 3,240 sI0.67 d5Gas Boiler OffsetMeter VerifyC/T 2,430 sI1.17 dCUSTOMERDairy & PaperDrying Lines6 / skids

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Source HX Titanium Welding3,060 s20 min94%98.2%68 (1.33 d)8
2. 2-Stage High-Temp Compressor3,780 s30 min91%97.4%610 (1.67 d)6
3. Flash Tank Steam Separator4,815 s40 min84%95.8%612 (2.00 d)4
4. SCADA COP >3.2 Commissioning3,240 s10 min96%98.6%25 (0.83 d)7
5. Gas Boiler Offset Meter Verify2,430 s8 min97%99.4%24 (0.67 d)10

Key figures

Takt time
4,500 s
Lead time
8.31 d
Value-added time
17,325 s
Process cycle efficiency (PCE)
7.7%
Rolled throughput yield (RTY)
89.8%
Customer demand per day
6 skids
Line capacity per day
4 skids
Bottleneck
Flash Tank Steam Separator

Reading the bottleneck

The bottleneck is "Flash Tank Steam Separator": it can process 4 skids per day against a demand of 6 skids, so it falls short of demand by 31.5%. Once downtime and scrap are counted, its cycle time grows from 4,815 s to 5,983 s, against a takt of 4,500 s. The largest loss at this step is equipment downtime (uptime 84%), about 917 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.

Other scenarios in this family

More scenarios of Decarbonization, Green Steel & Circular ESG: Decarbonization, Green Steel & Circular ESG