End-of-Life Solar PV Glass, Silver & Si Recovery
Product family: Zero-Landfill Panel Delaminate.
Flow: Repowered Utility Solar Parks → Al Frame & Junction Box Pull → Hot-Knife EVA Thermal Delam → Mechanical Glass Separation → Hydro-Acid Silver/Cu Leach → Cullet & Ingot Sale Certs → Glass & Silver Refineries
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. Al Frame & Junction Box Pull | 765 s | 20 min | 94% | 98.2% | 48 | 67 (1.40 d) | 64 |
| 2. Hot-Knife EVA Thermal Delam | 945 s | 30 min | 91% | 97.4% | 48 | 77 (1.60 d) | 49 |
| 3. Mechanical Glass Separation | 1,204 s | 40 min | 84% | 95.8% | 48 | 96 (2.00 d) | 34 |
| 4. Hydro-Acid Silver/Cu Leach | 810 s | 10 min | 96% | 98.6% | 19 | 43 (0.90 d) | 61 |
| 5. Cullet & Ingot Sale Certs | 608 s | 8 min | 97% | 99.4% | 14 | 34 (0.71 d) | 83 |
Key figures
- Takt time
- 1,125 s
- Lead time
- 7.89 d
- Value-added time
- 4,332 s
- Process cycle efficiency (PCE)
- 1.0%
- Rolled throughput yield (RTY)
- 89.8%
- Customer demand per day
- 48 tonnes
- Line capacity per day
- 34 tonnes
- Bottleneck
- Mechanical Glass Separation
Reading the bottleneck
The bottleneck is "Mechanical Glass Separation": it can process 34 tonnes per day against a demand of 48 tonnes, so it falls short of demand by 28.1%. Once downtime and scrap are counted, its cycle time grows from 1,204 s to 1,496 s, against a takt of 1,125 s. The largest loss at this step is equipment downtime (uptime 84%), about 229 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of Decarbonization, Green Steel & Circular ESG: Decarbonization, Green Steel & Circular ESG
- Direct Air Capture (DAC) Solid-Sorbent CO2 Pod
- Continuous Biomass Pyrolysis Biochar Carbon Sink
- 100% Hydrogen Direct-Reduced Iron (H2-DRI) EAF
- Cement Flue-Gas Post-Combustion Amine CCUS
- Closed-Loop Beverage Can-to-Can Al Remelt Line
- Used Cooking Oil (UCO) to Sustainable Aviation Fuel
- Black-Mass Lithium, Cobalt & Nickel Hydromet
- Captured CO2 + Green H2 e-Methanol Synthesis
- Automated Product Carbon Footprint (PCF) ISO-14067
- Industrial Waste-Heat Upgrade 150°C Steam Pump
- EU CBAM & EUDR Deforestation Supply-Chain Gate