Used Cooking Oil (UCO) to Sustainable Aviation Fuel
Product family: HEFA Bio-Jet Drop-In Fuel.
Flow: Filtered UCO & Tallow Tankers → Acid Degumming & Clay Bleach → Catalytic Hydrodeoxygenation → Selective Isomerization Crack → Fractionation SAF / Naphtha → ASTM D7566 Jet Blend & ISCC → Commercial Airline Hydrants
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. Acid Degumming & Clay Bleach | 344 s | 20 min | 94% | 98.2% | 160 | 224 (1.40 d) | 214 |
| 2. Catalytic Hydrodeoxygenation | 425 s | 30 min | 91% | 97.4% | 160 | 256 (1.60 d) | 165 |
| 3. Selective Isomerization Crack | 542 s | 40 min | 84% | 95.8% | 160 | 320 (2.00 d) | 117 |
| 4. Fractionation SAF / Naphtha | 365 s | 10 min | 96% | 98.6% | 64 | 144 (0.90 d) | 206 |
| 5. ASTM D7566 Jet Blend & ISCC | 273 s | 8 min | 97% | 99.4% | 48 | 112 (0.70 d) | 280 |
Key figures
- Takt time
- 506 s
- Lead time
- 7.82 d
- Value-added time
- 1,949 s
- Process cycle efficiency (PCE)
- 0.31%
- Rolled throughput yield (RTY)
- 89.8%
- Customer demand per day
- 160 batches
- Line capacity per day
- 117 batches
- Bottleneck
- Selective Isomerization Crack
Reading the bottleneck
The bottleneck is "Selective Isomerization Crack": it can process 117 batches per day against a demand of 160 batches, so it falls short of demand by 27.1%. Once downtime and scrap are counted, its cycle time grows from 542 s to 674 s, against a takt of 506 s. The largest loss at this step is equipment downtime (uptime 84%), about 103 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of Decarbonization, Green Steel & Circular ESG: Decarbonization, Green Steel & Circular ESG
- Direct Air Capture (DAC) Solid-Sorbent CO2 Pod
- Continuous Biomass Pyrolysis Biochar Carbon Sink
- 100% Hydrogen Direct-Reduced Iron (H2-DRI) EAF
- Cement Flue-Gas Post-Combustion Amine CCUS
- Closed-Loop Beverage Can-to-Can Al Remelt Line
- Black-Mass Lithium, Cobalt & Nickel Hydromet
- Captured CO2 + Green H2 e-Methanol Synthesis
- Automated Product Carbon Footprint (PCF) ISO-14067
- Industrial Waste-Heat Upgrade 150°C Steam Pump
- End-of-Life Solar PV Glass, Silver & Si Recovery
- EU CBAM & EUDR Deforestation Supply-Chain Gate