Hot-Caustic PET Bottle-to-Bottle Wash Line
Product family: Food-Grade Flake Pre-Clean.
Flow: Post-Deposit Curbside Bales → Bale Breaker & Hot Pre-Wash → Label Scraper & Wet Grinder → 85°C Caustic Friction Wash → Sink-Float Polyolefin Sep → Auto Optical Color/PVC Sort → SSP Food-Grade Pelletizers
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. Bale Breaker & Hot Pre-Wash | 471 s | 15 min | 95% | 98.5% | 88 | 132 (1.20 d) | 159 |
| 2. Label Scraper & Wet Grinder | 589 s | 20 min | 92% | 97.4% | 66 | 143 (1.30 d) | 120 |
| 3. 85°C Caustic Friction Wash | 788 s | 30 min | 84% | 95.8% | 88 | 198 (1.80 d) | 80 |
| 4. Sink-Float Polyolefin Sep | 530 s | 10 min | 95% | 98.8% | 44 | 99 (0.90 d) | 141 |
| 5. Auto Optical Color/PVC Sort | 398 s | 8 min | 97% | 99.4% | 28 | 66 (0.60 d) | 192 |
Key figures
- Takt time
- 736 s
- Lead time
- 6.83 d
- Value-added time
- 2,776 s
- Process cycle efficiency (PCE)
- 0.50%
- Rolled throughput yield (RTY)
- 90.3%
- Customer demand per day
- 110 tonnes
- Line capacity per day
- 80 tonnes
- Bottleneck
- 85°C Caustic Friction Wash
Reading the bottleneck
The bottleneck is "85°C Caustic Friction Wash": it can process 80 tonnes per day against a demand of 110 tonnes, so it falls short of demand by 26.9%. Once downtime and scrap are counted, its cycle time grows from 788 s to 979 s, against a takt of 736 s. The largest loss at this step is equipment downtime (uptime 84%), about 150 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of Water Desalination, Waste & Recycling MRF: Water Desalination, Waste & Recycling MRF
- 100,000m³/Day Seawater Reverse Osmosis Plant
- 50-Ton/Hr AI Robotic Municipal Recycling MRF
- Municipal Membrane Bioreactor (MBR) Reuse Plant
- Industrial Zero-Liquid-Discharge (ZLD) Brine Plant
- 1150°C Rotary Kiln Hazardous Chemical Destruction
- Urban Water Main Acoustic Leak Locate & Repair
- Thermal Hydrolysis Sludge-to-Biogas Dewater
- Red-Bag Hospital Bio-Waste Autoclave Shred Line
- High-Pressure Hydro-Jetting Storm Drain Loop
- End-of-Life Tire Recovered Carbon Black Pyrolysis
- 18.2 MΩ-cm Semicon Ultrapure Water (UPW) Skid