1150°C Rotary Kiln Hazardous Chemical Destruction
Product family: 99.9999% DRE Incineration.
Flow: Solvent Drums & Pharma Waste → Lab Fingerprinting & Blend → Drum Shredder & Lance Atomize → 1150°C Rotary Kiln & 2s After → Quench, Baghouse & Wet Scrub → CEMS Continuous Emission Out → Industrial Waste District Heat
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. Lab Fingerprinting & Blend | 576 s | 15 min | 95% | 98.5% | 72 | 108 (1.20 d) | 130 |
| 2. Drum Shredder & Lance Atomize | 720 s | 20 min | 92% | 97.4% | 54 | 117 (1.30 d) | 98 |
| 3. 1150°C Rotary Kiln & 2s After | 963 s | 30 min | 84% | 95.8% | 72 | 162 (1.80 d) | 66 |
| 4. Quench, Baghouse & Wet Scrub | 648 s | 10 min | 95% | 98.8% | 36 | 81 (0.90 d) | 115 |
| 5. CEMS Continuous Emission Out | 486 s | 8 min | 97% | 99.4% | 23 | 54 (0.60 d) | 157 |
Key figures
- Takt time
- 900 s
- Lead time
- 6.84 d
- Value-added time
- 3,393 s
- Process cycle efficiency (PCE)
- 0.61%
- Rolled throughput yield (RTY)
- 90.3%
- Customer demand per day
- 90 tonnes
- Line capacity per day
- 66 tonnes
- Bottleneck
- 1150°C Rotary Kiln & 2s After
Reading the bottleneck
The bottleneck is "1150°C Rotary Kiln & 2s After": it can process 66 tonnes per day against a demand of 90 tonnes, so it falls short of demand by 26.9%. Once downtime and scrap are counted, its cycle time grows from 963 s to 1,197 s, against a takt of 900 s. The largest loss at this step is equipment downtime (uptime 84%), about 183 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of Water Desalination, Waste & Recycling MRF: Water Desalination, Waste & Recycling MRF
- 100,000m³/Day Seawater Reverse Osmosis Plant
- 50-Ton/Hr AI Robotic Municipal Recycling MRF
- Municipal Membrane Bioreactor (MBR) Reuse Plant
- Industrial Zero-Liquid-Discharge (ZLD) Brine Plant
- Hot-Caustic PET Bottle-to-Bottle Wash Line
- Urban Water Main Acoustic Leak Locate & Repair
- Thermal Hydrolysis Sludge-to-Biogas Dewater
- Red-Bag Hospital Bio-Waste Autoclave Shred Line
- High-Pressure Hydro-Jetting Storm Drain Loop
- End-of-Life Tire Recovered Carbon Black Pyrolysis
- 18.2 MΩ-cm Semicon Ultrapure Water (UPW) Skid