50-Ton/Hr AI Robotic Municipal Recycling MRF

Product family: 95% Pure PET, HDPE & Al Bales.

Flow: Curbside Mixed Commingled → Bag Splitter & Trommel Screen → Ballistic 2D/3D Paper/Plastic → Optical NIR + AI Robot Pick → Eddy-Current Al Can Eject → Two-Ram High-Density Baling → Plastic & Paper Reprocessors

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: 50-Ton/Hr AI Robotic Municipal Recycling MRFSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Curbside Mixed Commingled → Bag Splitter & Trommel Screen (91.0 s) → Ballistic 2D/3D Paper/Plastic (114 s) → Optical NIR + AI Robot Pick (152 s) → Eddy-Current Al Can Eject (102 s) → Two-Ram High-Density Baling (77.0 s) → Plastic & Paper Reprocessors.SUPPLIERCurbside MixedCommingledI1.20 d1Bag Splitter &Trommel ScreenC/T 91.0 sI1.30 d2Ballistic 2D/3DPaper/PlasticC/T 114 sI1.80 d3Optical NIR + AIRobot PickC/T 152 sI0.90 d4Eddy-Current AlCan EjectC/T 102 sI0.60 d5Two-RamHigh-Density…C/T 77.0 sI1.00 dCUSTOMERPlastic & PaperReprocessors380 / tonnes

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Bag Splitter & Trommel Screen91.0 s15 min95%98.5%304456 (1.20 d)544
2. Ballistic 2D/3D Paper/Plastic114 s20 min92%97.4%228494 (1.30 d)409
3. Optical NIR + AI Robot Pick152 s30 min84%95.8%304684 (1.80 d)274
4. Eddy-Current Al Can Eject102 s10 min95%98.8%152342 (0.90 d)483
5. Two-Ram High-Density Baling77.0 s8 min97%99.4%95228 (0.60 d)652

Key figures

Takt time
142 s
Lead time
6.81 d
Value-added time
536 s
Process cycle efficiency (PCE)
0.15%
Rolled throughput yield (RTY)
90.3%
Customer demand per day
380 tonnes
Line capacity per day
274 tonnes
Bottleneck
Optical NIR + AI Robot Pick

Reading the bottleneck

The bottleneck is "Optical NIR + AI Robot Pick": it can process 274 tonnes per day against a demand of 380 tonnes, so it falls short of demand by 27.9%. Once downtime and scrap are counted, its cycle time grows from 152 s to 189 s, against a takt of 142 s. The largest loss at this step is equipment downtime (uptime 84%), about 29.0 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.